Delivery times

Every month of waiting costs you money

On the power transformer market demand exceeds supply and manufacturers’ lead times keep growing. TRAFOSYNC delivers transformers in up to 9 months.

TRAFOSYNC supplies transformers to your order in up to 9 months
Power transformer on a heavy-haul trailer

Comparison of power transformer delivery times in 2025–2026 (in months)

TRAFOSYNC
Schneider Electric France
18–26
TMC (Italy)
20–28
Efacec (Portugal)
20–28
Pauwels (Belgium)
24–32
Hitachi Energy (ex-ABB)
48–60
Siemens Energy (Germany)
48–60

Indicative data for medium-power transformers (10–100 MVA), source [3]. Ranges differ slightly between publications. The TRAFOSYNC transformer delivery time is the company’s commitment.

EVERY MONTH OF WAITING FOR A TRANSFORMER COSTS YOU MONEY.

A SHORT DELIVERY TIME EARNS YOU EXTRA PROFIT.

TRAFOSYNC transformers: delivery in up to 9 months. Quality supervision by TÜV Rheinland available upon the Customer’s request.

Savings calculator →
Market

Typical delivery times and shortage

18–30 mo.

Medium power, 5–60 MVA

Delivery times on the transformer market, 2026. According to TransNine Electric.

> 24 mo.

Above 100 MVA

Delivery times on the transformer market, about 110–160 weeks or more. According to TransNine Electric and McKinsey & Company.

914 GVA

Demand, 2025

Source [1].

566 GVA

Supply, 2025

Shortage of about 38% of demand. Source [1].

Sources

  1. McKinsey & Company, “The transformer supercycle: Why demand is outrunning supply” (2026) — power transformer demand and supply in 2025, GVA; cites Cwieme Berlin, “24+ month lead times: New normal for transformer suppliers” (17 March 2026). mckinsey.com
  2. TransNine Electric, “Transformer Lead Times: How Long to Expect in 2026” — delivery times by power class. transnineelectric.com
  3. GridReadiness, “Transformer Lead Times Europe 2026” — lead times of Schneider Electric France, TMC, Efacec, Pauwels, Hitachi Energy and Siemens Energy (GridReadiness publication). gridreadiness.com
  4. GridReadiness, “Pauwels vs Efacec vs GE Vernova: Transformer Lead Times Compared” — comparison of Efacec and Pauwels lead times. gridreadiness.com

Data as of November 2026; estimates by analysts and consultants, not official statistics.