Transformer delivery time
Every month of waiting costs you money
On the power transformer market demand exceeds supply and manufacturers’ lead times keep growing. TRAFOSYNC delivers transformers in up to 9 months.
TRAFOSYNC supplies transformers to your order in up to 9 months
Comparison of power transformer delivery times in 2025–2026 (in months)
Indicative data for medium-power transformers (10–100 MVA), source [3]. Ranges differ slightly between publications. The TRAFOSYNC transformer delivery time is the company’s commitment.
EVERY MONTH OF WAITING FOR A TRANSFORMER COSTS YOU MONEY.
A SHORT DELIVERY TIME EARNS YOU EXTRA PROFIT.
TRAFOSYNC transformers: delivery in up to 9 months. Quality supervision by TÜV Rheinland available upon the Customer’s request.
Savings calculator →Typical delivery times and shortage
Medium power, 5–60 MVA
Delivery times on the transformer market, 2026. According to TransNine Electric.
Above 100 MVA
Delivery times on the transformer market, about 110–160 weeks or more. According to TransNine Electric and McKinsey & Company.
Sources
- McKinsey & Company, “The transformer supercycle: Why demand is outrunning supply” (2026) — power transformer demand and supply in 2025, GVA; cites Cwieme Berlin, “24+ month lead times: New normal for transformer suppliers” (17 March 2026). mckinsey.com
- TransNine Electric, “Transformer Lead Times: How Long to Expect in 2026” — delivery times by power class. transnineelectric.com
- GridReadiness, “Transformer Lead Times Europe 2026” — lead times of Schneider Electric France, TMC, Efacec, Pauwels, Hitachi Energy and Siemens Energy (GridReadiness publication). gridreadiness.com
- GridReadiness, “Pauwels vs Efacec vs GE Vernova: Transformer Lead Times Compared” — comparison of Efacec and Pauwels lead times. gridreadiness.com
Data as of November 2026; estimates by analysts and consultants, not official statistics.